Annual ARC Maintenance Update - Part 2

September 26, 2018
Annual ARC Maintenance Update - Part 2

Maintenance Continued: The major project that occurred during the 2018 fall closure was the replacement of two warrantied boilers. The Recreation team hired an engineer team to help re-design these boilers with new piping, pump redundancies and new equipment to help the facility be more efficient.   This projects was originally scoped at taking 2 month to complete with a large price tag.  Most of the work was done in-house by the Recreation maintenance team (Brad, Patrick, Oscar, Tony).  This team put in many hours to install these boilers as quick as they could and were successful in getting these boilers operational in two weeks and the building reopened. This team installed this new system in a quarter of the time and a third of the cost.  Thank you Team!